The Gantt tab

What depends on what — and why the base chart never moves your dates.


Timeline answers *how is it going?* Gantt answers *what depends on what?* Add it from the + at the end of the tab strip; it earns its place on projects with real dependencies.

  • One row per dated task in schedule order, indented by chain depth like a work-breakdown structure.
  • Real finish-to-start arrows drawn from prerequisite to dependent. The edges are the same "blocked by" links you set in a task's detail.
  • The same milestone rail as the Timeline, and bars coloured by the same schedule-health engine — so "Delayed" means one identical thing in both tabs.
  • A Dependency conflicts counter: how many tasks start before the work they depend on finishes.
The base chart flags, it never reschedules

Noots will tell you that a task starts before its prerequisite finishes, and leave every date exactly where you put it. Automatically shifting other people's work is something a project manager should opt into — so it lives in the Hard-Dependency Gantt extension, which ships with the Engineering & Construction preset and is installable on any workspace.

With that extension installed, an illegal drag is refused or warned, a legal move cascades downstream while preserving each task's duration, and a scheduled sweep ripples real slips with an audit row explaining every move. Dependencies themselves are on the Team plan and above.